  • 21 May 1991

    The Fuel Pipeline Transportation Limited (FPT) was found on 21 May 1991 by the cabinet resolution subjected mainly to reduce the number of road and rail fuel transportation vehicles transiting on Bangkok Metropolitan and vicinity areas.

    28 June 1991

    According to the resolution of the cabinet, The Thai Airways International Public Company Limited acts as the pivotal joint ventures to establish the company named “Fuel Pipeline Transportation Limited (FPT)”.

  • 24 February 1992

    To construct the pipeline system route Bangchak-Donmuang-Bang Pa-In, the company was sign the loan agreement with bank and financial institutions.

    21 September 1992

    Fuel Pipeline Transportation Limited (FPT) conducts the foundation stone laying ceremony at head office.

  • 9 February 1993

    Fuel Pipeline Transportation Limited (FPT) signed the construction agreement with Index international group company limited and pencol engineering consultant company limited to construct the Bang Pa-In and Chaing Rak Noi depot

  • 5 January 1994

    The first day of operate by transport aviation fuel from main supplies sources, which are Bangchak refinery, Shell Depot and Chevron Depot at Chongnonsi to Donmuang Depot.

    30 March 1994

    The first day of operate the ground products via FPT pipeline system to Bang Pa-In depot

    19 May 1994

    The first day of ground product road loading operation to tank tuck at Bang Pa-In depot

    19 May 1994

    Her Royal Highness Princess Maha Chakri Sirindhorn presided over the grand opening ceremony of Fuel Pipeline Transportation Limited.

    21 May 1994

    Fuel Pipeline Transportation Limited (FPT) has been received the investment privileges offered by Board of Investment (BOI) on category 6.18 with patent no. 1079/2535

    7 October 1994

    The first day of ground product rail loading operation at Chaing Rak Noi Depot

  • 3 March 1999

    Fuel Pipeline Transportation Limited (FPT) responsed to the financial crisis impact on the managed float of Thai baht by being the first company in Thailand to restructure its loan with creditor groups. The ceremony of first restructure loan held at Bank of Thailand (BOT).

  • 6 March 2006

    The first day of operate by transport aviation fuel from main supplies sources that are Bangchak refinery, Shell Depot and Chevron Depot at Chongnonsi via pipeline system of JP-One Asset Co., Ltd., which connected to the pipeline system of FPT at Makasan off-take Station.

  • 8 October 2010

    Fuel Pipeline Transportation Limited (FPT) was received the quality management system ISO 9001:2008 certificate from Bureau Veritas (Thailand) Ltd.

  • 22 July 2011

    Fuel Pipeline Transportation Limited (FPT) had been operated for 20 years. The 20 year anniversary ceremony was held at head offices.

    2 November 2011

    Bangkok Aviation Fuel Service Public Company Limited (BAFS) take over FPT with the number of issued shares holder 95 %. FPT become the subsidiary of BAFS

  • 21 December 2015

    M.R. Supadis Diskul, Chairman of Fuel Pipeline Transportation Limited, signed a memorandum of cooperation in expanding the Fuel Pipeline Transportation system to the north. With Mr. Withun Kulcharoenwirat Director of the Department of Energy and Gen. Anantaporn Kanchanarat, Minister of Energy. The ceremony was held on 21 December 2015 at 9:30 am at the Ministry of Energy, Energy Complex Center.

  • 23 August 2016

    Mr. Palakorn Suwanrath (Privy Councilor) presided over the Groundbreaking ceremony of Northern Fuel Pipeline Transportation Project, Phichit Depot. The ceremony was held on 23 August 2016 at Phichit Depot, Wachirabarami District, Phichit Province.

    23 November 2016

    Lt.Gen. Wichak Siribunsop presided over the groundbreaking ceremony of Northern Fuel Pipeline Transportation Project, Lampang Depot. The ceremony was held on 23 August 2016 at Lampang Depot, Sobprap District, Lampang Province.

  • 27 March 2019

    Mr. Siri Jirapongphan Ministry of Energy Presided over the grand opening ceremony of Northern Fuel Pipeline Transportation Phase 1 (Bangpa In – Kamphaeng Phet- Pichit). The ceremony was held on 27 March 2019 at Pichit Depot Wachirabarami District, Phichit Province.